Make every effort to promote the construction of the new sea outlet in Tongzhou Bay, making the dream of a large port a reality


Release time:

2023-05-19

Make every effort to promote the construction of the new sea outlet in Tongzhou Bay, making the dream of a large port a reality

Construction of the Tongzhouwan Port Area's Three Harbors Pool No. 1-3 Wharf Project began in early 2022. As of now, the overall progress of the lead embankment has reached 78%, and the overall progress of the wharf has reached 65%. It was awarded the provincial "Demonstration Project" of Jiangsu Province's Highway and Water Transport Engineering Safety Construction in 2022. On the road to progress, countless Tongzhouwan people have taken on the responsibility of "first-person perspective", with a more energetic spirit, serving the construction of the new seaport. Multiple departments have coordinated and cooperated to fully promote the construction of the Tongzhouwan main port area, allowing the "seaport dream" in the hearts of the people of Tongzhouwan to gradually become a reality.

Meticulous Organization, Exceeding Expectations

As a starting project for the construction of the new seaport, the wharf project has received much attention from all sectors of society since its commencement. The high construction difficulty and the large number of participating parties have presented significant challenges to project management. As the leading department, the Demonstration Zone Port Administration Bureau actively played a bridging role, organizing a special meeting on offshore auxiliary construction platforms to address the issue of access for offshore sand-filling equipment. It scientifically arranged the work of multiple parties, reducing the impact of cross-operational work among construction equipment, and fully consolidating the strengths of various participating units to fully ensure project implementation. Ultimately, by the end of 2022, the project's lead embankment formed a construction channel, exceeding the predetermined targets for 2022 and laying a solid foundation for the project's advancement in 2023.

Unwavering Struggle, Unity of Effort

The wharf project is located in offshore operations and is significantly affected by sea weather.

To meet the node deadlines, Nantong Port Construction Investment Company, as the construction unit, implemented a reverse schedule, insisting on detailed daily arrangements for project planning and construction progress, and promptly analyzing key challenges encountered during construction. The project leadership team conducted on-site inspections and supervision, department heads provided on-site monitoring, and various teams rationally allocated personnel for construction to ensure continuous project progress. At the same time, it strengthened control over the construction site, setting plans, tasks, timelines, and rewards and penalties for various participating units, strictly implementing the assessment system, enhancing the sense of responsibility and urgency of all project personnel in completing the construction plan, and inspiring the confidence and fighting spirit of all project personnel in ensuring high-quality and timely construction progress.

Technological Empowerment, Safety Assurance

 

The project focuses on building a high-standard temporary wharf and a full-process, all-round modular safety operation platform, continuously strengthening technological innovation and conducting in-depth research on relevant topics. During the project construction, China Communications Third Harbor Bureau, the construction unit, fully leveraged its technological advantages, successfully overcame technical challenges, and successfully applied for multiple utility models and invention patents, including intelligent control equipment for ship collision prevention applicable to offshore wharf construction and safety protection devices for high-pile hoop installation. The project team, closely focusing on the goal of the provincial "Demonstration Project" of safety construction, used innovative technology to support safe production and ensure the steady progress of the project. In September 2022, when super typhoon "Hinnamnor" passed through Tongzhouwan, the project department promptly used protective technology to provide scientifically reliable protection for the main project, carried out comprehensive and efficient evacuation of ships and personnel, and established a complete emergency system to maximize the safety of the project and personnel. The project was awarded the provincial "Demonstration Project" of safety construction in 2022.

In the future, the demonstration zone will focus on the primary task of high-quality development, focusing on national and provincial major strategies such as the development of the Yangtze River Economic Belt, the integrated development of the Yangtze River Delta, and a strong maritime province, making great efforts in the integration of river and sea transportation, making comprehensive use of land and sea resources, and promoting high-quality development of the Tongzhouwan port, industry, and city.